2008년 하반기 DECK
MAINTENANCE Result |
LNGC
SK Splendor |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
2008.12.31 |
Item |
Area |
작업 주기 |
작업 기간 |
Last date of Done |
Work Schedule / Action |
수행률 (%) |
Remarks (for Additional) |
7월 |
8월 |
9월 |
10월 |
11월 |
12월 |
DECK
& OUTFITTING |
FORECASTLE
DECK - Including BSN Store
(PLATE, STRUCTURES, MOORING OUTFITTINGS) |
12M |
2W |
May. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
TRUNK DECK - Including Dome & Side Passage Way
(PLATE, STRUCTURES, LIGHTING POST, Fwd. MAST) |
12M |
6W |
Dec. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
D/P TK.RM VENT 4PCS 신환 |
|
|
|
|
|
|
|
|
50 |
LIQUID
DOME BEARING PLATE 신환(8PC) |
UPPER DECK - Including M/F Upp.-Dk. Part
(PLATE, STRUCTURES, PILOT LADDER &
GANGWAY,
MOORING OUTFITTINGS, LIGHTING POST, BOAT DAVIT) |
12M |
4W |
Oct. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
BOAT
PENDANT 취부 |
POOP DECK - Including Steering Gear Room
(PLATE, STRUCTURES, MOORING OUTFITTINGS, Aft.
MAST) |
12M |
2W |
Jan. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
CARGO CONCERN LINES TOUCH UP & FREE-UP
(CARGO V/VS & LINES WITH SUPPORT, VENT
POST,
N2 V/VS & LINES WITH SUPPORT + NAME PLATES) |
12M |
2W |
Nov. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
40 |
ESD,
D/S V/V OVHL, IBS/IS N2 V/V
점검, V/V HANDLE 정비 |
SUPERSTRUCTURE |
ACCOMODATION
(PLATE, STRUCTURES, ALL KIND OF PIPE &
SUPPORT,
DUCT & DAMPER, WING & TOP BRIDGE, MAIN MAST) |
12M |
4W |
Oct. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
70 |
UPP. ~ E DK.
정비완료 |
ENGINE ROOM CASING
(PLATE, STRUCTURES, DUCT & DAMPER, FUNNEL
DK.) |
12M |
4W |
Dec. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
10 |
|
MANIFOLD (Port & Stb'd) |
12M |
4W |
Dec. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
15 |
|
CARGO MACHINERY & MOTOR ROOM CASING |
12M |
1W |
Apr. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
GEAR |
MOORING
WINCH/WINDLASS & LADDER/GANGWAY
(WINCH/WINDLASS BODY & SUPPORT ) |
12M |
2W |
May. 2008 Dec. 2008 |
|
|
|
|
|
닻 CABLE용
LUG 설치 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
HANDRAIL 정비 |
|
|
|
50 |
LADDER/GANGWAY REGULATOR 4SETS
신환 |
DAVIT & CRANE
(SPACE & P'P DAVIT, HOSE HANDLING, MONORAIL, PROVISION) |
12M |
3W |
Jan. 2008 |
|
|
|
|
MO. LIMIT SW. 4PCS 신환 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
MO. BLOCK OVHL |
|
|
|
|
- |
NO.1 PR. LO
GAUGE 신환 |
LUBRIC. |
VENTILATOR MANUAL HANDLE
GREASING |
6M |
2D |
Dec. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
|
ESD & CARGO V/Vs FREE-UP & GREASING |
6M |
3D |
Nov. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
50 |
SNRI V/V
GREASE 신환 |
CRANE & DAVIT / MOORING WIREs GREASING |
6M |
1W |
Dec. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
|
MOORING EQUIPMENT FREE-UP & GREASING |
6M |
1W |
Nov. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
|
SPECIAL |
SAFETY
EQUIPMENT
(FIRE
FIGHTING EQUPIMENT & LIFE SAVING APPLIANCES) |
1M |
1W |
Dec. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
ISO. V/V 정비 |
|
|
|
|
|
|
|
80 |
구명정
이탈장치 정비 |
ENCLOSED SPACEs (VOID SPACE & PIPE DUCT) |
6M |
1W |
Oct. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
P/D
LO 누설부 점검/소제 |
WATER SPRAY NOZZLEs FREE-UP (ACCOMM.
& DECK) |
12M |
1W |
Oct. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
NOXXLE,
PIPE OVHL 실시 |
VENTILATOR HEAD & SCREEN OVHL |
12M |
2W |
Jun. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
- |
|
WATER BALLAST TANK MAINTENANCE WORK |
2.5Y |
2W |
Oct. 2007 |
|
- |
|
WATER BALLAST TANK MUD
CLEANING (for D/D) |
2.5Y |
2W |
Oct. 2007 |
|
- |
|
INSPEC. & TEST |
WBTs & VOID SPACEs
INSPECTION |
6M |
5D |
Sep. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
매년 9월 점검 |
WINCH BHC & BRAKE LINER MEASURING |
12M |
2D |
Oct. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
매년 10월 검사 |
INDOOR |
PUBLIC AREA
SOAPING & WAXING, TILE REPAIR |
12M |
1W |
Dec. 2008 |
2/E 욕실 타일 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
Galley,
해수탕 타일작업 |
CABIN CARPET CLEANING (During a Rainy Day
or a Rough Sea) |
2M |
2D |
Dec. 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
100 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
*
Remarks : |
1. Jisepo Waiting - 7/15 ~ 8/15 (31일간 Anchoring) |
|
|
: Planned Job |
|
2. 2008년 하반기 주 정비작업은
Accomodation 및 Upper
deck 청락 / 도장작업이었음. |
|
|
: Additional Job |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|